Storm Water Pump Station Update

The storm water pump station final plat is receiving final City signatures and associated municipal permits with the project have all been obtained by the District.

The City of Missouri City has approved the final construction drawings and the District should receive the signed plans the week of March 29th.

Pending resolution of any last-minute design improvements along with project advertisement, bidding, and contractor award schedule; it is anticipated construction on the facility will commence early Summer 2021.